Projects
-
Canal Street Project
-
Community Safety
-
Cultural Plan
-
Rec & Parks Projects
-
Solid Waste Program
-
Town Plan 2026
-
Water & Sewer Rate Study
-
Western Ave. Intersection Project
Water & Sewer Rate Study
In December 2024, a contract was awarded to NewGen Strategies & Solutions to complete a comprehensive study of the Brattleboro’s water and sewer rate structure.
Representatives from NewGen attended a Brattleboro Selectboard meeting on February 4, 2025, to discuss their rate study process. The group will be meeting with Town staff regularly throughout the late winter and early spring. NewGen presented the results of its study to the Selectboard on May 20.
View NewGen's initial presentation on this project: PowerPoint, Watch
Timeline
The following chart outlines NewGen's proposed timeline for its study along with the utility budget more broadly.
Jan. 9, 2025 | Preliminary kickoff meeting with staff |
Feb. 4, 2025 | Kickoff presentation to the Selectboard – PowerPoint, Watch |
Virtual status meeting to discuss revenue requirements with staff | |
In-person presentation of revenue requirements and preliminary required revenue adjustments | |
Virtual status meeting to discuss preliminary findings with staff | |
Virtual status meeting to discuss revised findings with staff, if needed | |
May 20, 2025 | In-person presentation of the results of the study to the Selectboard — Memo, PowerPoint, Watch |
June 3, 2025 | FY26 Utility Budget Overview — Memo |
June 17, 2025 | Utility Budget: Alternate Rates — Memo |