Paving Updates – Sept. 25, 2026
The Vermont Agency of Transportation (VTrans) is providing regular updates about construction projects in Brattleboro. The latest update from VTrans was published on Sept. 25, 2026.
Fill out this form to receive email alerts about these projects directly from VTrans.
Overnight work is planned for Friday, September 25, 2026 from 7 p.m. to 6 a.m.
Traffic Impacts
Vermont Route 9: (Night Work) — Single-lane closures with alternating traffic patterns controlled by flaggers are planned from the Exit 2 interchange to the Edward Heights intersection from 7 p.m. to 6 a.m. Monday night through Saturday morning. No street-side parking will be available through the work zone. Motorists should watch for wet paint.
U.S. Route 5: Brattleboro (Night Work) — From 7 p.m. to 6 a.m. Monday night through Saturday morning, single-lane closures will be in place on U.S. 5 from the intersection with Noah's Lane through the Exit 3 roundabout to the Old Ferry Road intersection. Flaggers and uniformed traffic officers will assist traffic through alternating traffic patterns.
U.S. Route 5: Brattleboro-Putney (Day Work) — Monday through Friday from 6:30 a.m. to 3:30 p.m. single-lane closures will be in place as needed on U.S. 5 on the bridge over Interstate 91 between Bennett Drive and Old Ferry Road. Flaggers will control alternating traffic patterns through the work zones.
Final pavement on U.S. 5 with permanent lines in progress.
Construction Activities
Vermont Route 9: (Night Work) — Crews will begin painting as they are freed up on U.S. 5. The paint work is scheduled into Saturday mornings and motorists should watch for wet paint.
U.S. Route 5: Brattleboro (Night Work) — Permanent pavement marking application will continue on U.S. 5. The paint crew will be working on permanent markings into Saturday mornings. In addition, some night work operations are scheduled for Bridge 10B - the I-91 overpass between Old Ferry Road and Bennett Drive - and work zones may be present for milling and paving once repairs are complete.
U.S. Route 5: Brattleboro-Putney (Day Work) — Work on the I-91 overpass between Old Ferry Road and Bennett Drive will continue next week. Paving operations for this will be done at night once repairs are complete to avoid traffic delays.