Paving Updates – July 31 to August 3
The Vermont Agency of Transportation (VTrans) is providing regular updates about the paving project in Brattleboro. The latest update from VTrans was published on July 29, 2026. Fill out this form to receive email alerts about this project directly from VTrans.
Overnight work is planned for this Friday, July 31 and Sunday, August 2, 2026.
Friday, July 31, into Saturday morning, August 1, crews will continue paving on U.S. Route 5 between Noah's Lane and Bennett Drive. Single-lane closures will be in place and uniformed traffic officers and flaggers will direct traffic through alternating traffic patterns as needed.
The on- and off- ramps in all directions for Interstate 91 Exit 3 are planned to be closed from 12 a.m. to 5 a.m. Saturday morning, August 1.
Sunday, August 2, into Monday morning, August 3, guardrail work is planned for Vermont Route 9 between the I-91 Exit 2 interchange and Edward Heights intersection in West Brattleboro. This crew will work off the shoulder as much as possible with uniformed traffic officers providing a follow-along vehicle. Flagger controlled single-lane closures through the work zone will be in place as needed.